Week 1&2 February 15th -28th - Project Selection and Supply Attainment -- DONE!!!
Week 3 - March 1 - 7 - Paper Preparation - cut out and bag you papers according to your pattern. - DONE!!!!
Week 4 - March 8 - 14 - Sewing A Arcs - there are multiple sets of these and we are going to spend multiple weeks working on them. Some done.....lots left
Week 5 - March 15-21 - Sewing A Arcs - just keep sewing!!!! With a crazy week and the beginning of market madness (as opposed to March Madness), I didn't get a lot done, but I am making steady progress, completing 1 or 2 sets each evening, so far I am up to 11 sets of As and 7 sets of Bs, so approaching half way.
Week 6 - March 22-28 - Sewing B Arcs - just keep going! We got this far, we can do it! See note above.
Week 7 - March 29 - April 4 - Sewing B Arcs - This week!!! It's the last week of ARCS, and while there is NO way I will get them finished this week, I am determined to keep going, and get as far as I can.
Week 8 - April 5 - April 11 - Using QW Wedding Ring Rulers - Cutting out backgrounds -- Asteroids and Melons.
Week 9 - April 12 - April 18 - Pieced Asteroids and Melons
Week 10 - April 19 - April 25 - Assembly
Week 11 - April 26 - May 2 - Assembly
Week 12 - May 3 - May 9 - Assembly
Week 13 - May 10 - May 16 - Assembly
Week 14 - May 17 - May 23 - Applique - Fused
Week 15 - May 24 - May 31 - Applique - Hand Turned
How are you coming along on this project??