Week 1&2 February 15th -28th - Project Selection and Supply Attainment -- DONE!!!
Week 3 - March 1 - 7 - Paper Preparation - cut out and bag you papers according to your pattern. - DONE!!!!
Week 4 - March 8 - 14 - Sewing A Arcs - there are multiple sets of these and we are going to spend multiple weeks working on them. Well, I am way, way behind. I managed to get 3 sets done, out of 12, leaving me with 9 uncompleted sets (yikes)!! SO, I am WAY WAY behind, and this week is not a good week to catch up given all of the things on the plate. I wanted to get ahead this past week so that I could slack a little this week!!! Maybe I can catch up during the B series week!!! I better or I am in deep trouble!
Week 5 - March 15-21 - Sewing A Arcs - just keep sewing!!!! This week will be a light week on the QAL front, as I am prepping for both a show and a retreat next weekend, and a full work schedule.
Week 6 - March 22-28 - Sewing B Arcs -
Week 7 - March 29 - April 4 - Sewing B Arcs -
Week 8 - April 5 - April 11 - Using QW Wedding Ring Rulers - Cutting out backgrounds -- Asteroids and Melons.
Week 9 - April 12 - April 18 - Pieced Asteroids and Melons
Week 10 - April 19 - April 25 - Assembly
Week 11 - April 26 - May 2 - Assembly
Week 12 - May 3 - May 9 - Assembly
Week 13 - May 10 - May 16 - Assembly
Week 14 - May 17 - May 23 - Applique - Fused
Week 15 - May 24 - May 31 - Applique - Hand Turned